Hm i think all you want to do is open the workflow editor, jlick settings config and set the "max jobs per priority class to 5

Max queued jobs you normally dont care about but max running everyone cares about.
emcodem, wrapping since 2009 you got the rhyme?
buddhabas
Posts: 19
Joined: Tue Oct 04, 2022 9:03 pm

Re: setting max parallel running jobs

Post by buddhabas »

emcodem wrote: Wed Dec 18, 2024 10:52 pm Hm i think all you want to do is open the workflow editor, jlick settings config and set the "max jobs per priority class to 5

Max queued jobs you normally dont care about but max running everyone cares about.
It does work!